Summary:
- Traffic Management
- QA/WHS/Environmental Management
- Project Management
- Temporary Water Diversion Measures
- Installation of Environmental Controls
- Culvert Construction Works
- Installation of Piers/Piles
- Construct western wing wall and excavate to install culvert sections
- Installation of precast culverts and backfilling
- Supply and install rip rap and energy dissipaters
- Construction of eastern wing wall
- Install guardrail
- Construction of Footpath
- Road Reinstatement
- Water Main Adjustment works
- Excavation
- OD168 SCL pipe (6mm) – Concrete Encased – Reinforced
- OD273 SCL pipe (6mm) – Concrete Encased – Reinforced
- Provide standard fittings & bends with anchor blocks where required including installation accordance with applicable DTC
- Supply and compact Stabilised Sand
- Connections to Sydney Water Mains
- Install Guardrail
- Site rectification