Barrengarry Mountain – Slip Repair and Embankment Stabilisation

Summary:

  • Landslip due to severe storm.
  • RMS road at risk of collapse
  • Provide Traffic Management
  • Gain access down severely unstable treacherous slope
  • Using anchor and winch system to track excavator to base of landslide
  • Created a site specific materials handling system in difficult site conditions

Scope:

  • Install geo fabric
  • Install geo grid
  • Build up in layers using granular materials
  • Continue to build layers to a height of 1.2m
  • Install large armour rocks
  • Build retaining wall adjacent to road
  • Install guard rail