The works includes but not limited to reinstating portion of collapsed creek embankment. Earthworks, embedment of large toe rock, import and placement of 270T of 150- 300mm rock armour, import and placement of 900T of 500- 800mm rock armour, stormwater drainage, landscaping, supply and installation of guardrail and coper logs asphalt reinstatement.
Cadifern proudly completed the project meeting all the relevant legal and other requirements and ensuring that our final product was not only of high quality but visually pleasing for the community.
Our project scope was completed in August 2022 within the program and budget.
The client and the community were pleased with our performance, diligence, and successful project completion